← Infrastructure/Microsoft Azure East Africa (Olkaria / Nairobi)

Microsoft Azure East Africa (Olkaria / Nairobi)

D

Nairobi / Olkaria, Kenya · KE · Microsoft Corporation

AnnouncedAI-Capable HyperscaleUnder Review

Environment

Water Stress
lowB

WRI Aqueduct 4.0, 2023, 2023

Aquifer Stress
Not DisclosedND
Grid Carbon Intensity
57 gCO₂/kWhA

IEA Electricity Information 2022, Kenya, 2022

Grid RegionKenya National Grid (KETRACO/KenGen)
Drought Risk
low

Kenya Meteorological Department, 2023

Environmental Review
pending

Kenya National Environment Management Authority (NEMA)

Facility

CategoryAI-Capable Hyperscale
StatusAnnounced
CapacityNot DisclosedND
Location
-0.9000, 36.2900 · KE
RegionNairobi / Olkaria, Kenya
Research statusUnder Review
Last verified2026-05-01

Evidence (2 sources)

Journalism2024-05-22Microsoft News

Confirms $1B investment, geothermal power intent, and Kenya as the target country for the East Africa initiative.

Microsoft and G42 announced a $1B initiative targeting AI infrastructure in Kenya, including a geothermal-powered data center campus in the Olkaria zone.
Journalism2026-02-01Tom's Hardware

Documents current stalled status from trade press — site remains announced but uncertain.

Reports indicate the Microsoft/G42 Kenya data center negotiations have stalled as of early 2026 due to disagreements over grid capacity commitments.