Microsoft Azure Kemps Creek Data Centre Campus
BSydney, New South Wales, Australia · AU · Microsoft Corporation
Under ConstructionAI-Capable HyperscaleVerified
Environment
Water Stress
mediumB
WRI Aqueduct 4.0, 2023, 2023
Aquifer Stress
Not DisclosedND
Grid Carbon Intensity
680 gCO₂/kWhB
IEA Electricity Information 2022, Australia, 2022
Grid RegionNational Electricity Market NSW (AEMO)
Drought Risk
medium
Bureau of Meteorology, Australia, 2023
Environmental Review
approved
Penrith City Council / NSW Department of Planning
Facility
CompanyMicrosoft Corporation
CategoryAI-Capable Hyperscale
StatusUnder Construction
Capacity
190 MWB
190 MW campus capacity per Microsoft official Kemps Creek project page. Two 2-story buildings; $1.3B AUD investment. Building 1 targeted for 2025–2026.
Location
-33.8700, 150.7700 · AU
RegionSydney, New South Wales, Australia
Research statusVerified
Last verified2025-05-01
Evidence (1 source)
Government2024-01-01Microsoft Local (Australia)
Primary source confirming 190 MW capacity, $1.3B investment, and Kemps Creek location from Microsoft's own communications.
Microsoft's official Kemps Creek project page describes a $1.3B AUD two-building campus totalling 190 MW IT load in Western Sydney.
← Back to mapRecord updated 2026-06-01